Milestone N#Milestone nameRelated WP/TaskDue date (M)Means of verification
MS1.1Kick-off meeting1.13Report
MS1.2Risk register update1.124Report
MS1.3Documentation management available1.23Report
MS1.4Health and safety survey completed 1.35Report
MS1.5Workshop with technology clusters1.436Report
MS2.1Communication strategy implementation2.118Report
MS2.2First CBI completed2.218Report
MS2.3Draft framework for sustainability LCA and DS4 seminar concept2.330Report
MS3.1Innovation Training Curriculum defined3.118Report
MS3.2Report from AIPF meetings and expert workshops3.224Report
MS3.3Topical mini workshops on particle therapy technologies3.318Indico page
MS3.4Technology validation workshop with focus on plasma/muon3.430Report
MS4.1Thin Film SRF workshop and lead roadmap discussion4.110Report
MS4.2Existing cryostat refurbished and commissioned for use with Nb3Sn cavities, coupler adaptation4.228Report
MS4.3Report on different types of 1.3 GHz cavity manufacturing and surface preparation4.322Report
MS4.4Test for development of small scale Nb3Sn targets4.424Report
MS5.11st deployment of novel SiC-based mirror in laser system5.136Measurement rep.
MS5.2First deployment of novel beam sampler in laser system5.236Measurement rep.
MS5.3Successful demonstration of autonomous tuning5.324Measurement rep.
MS5.4Realisation of the capillary5.428Prototype
MS5.5Realisation of dielectric structure5.528Prototype
MS6.1Cathode and anode produced6.125Measurement rep.
MS6.2Pulser V1 development completed6.215Measurement rep.
MS6.3FE-FRT V1 development completed6.220Measurement rep.
MS6.4Wide tape development6.336Measurement rep.
MS7.1Workshop on adjustable PM magnet technologies7.110Report
MS7.2Workshop on present and future magnet requirements7.219Report
MS7.3Specifications of the PMW7.312Report
MS7.4Magnetic design of the PMW7.324Report
MS8.1Report on HTS characterisation and quench studies8.218Report 
MS8.2Conceptual design of energy-saving split coils completed, construction started8.321Report
MS8.3HTS cable sample ready for testing8.424Report
MS9.1Design of the chirping cavity complete9.118Report
MS9.2Design of the transverse deflecting structure completed9.218Report
MS10.1Single- to multi- cell transfer & ALD-doped cavity tested10.136Report
MS10.2Cobot operational for HPR R&D in clean room10.224Report
MS10.3Specification of diagnostic performance requirements for cavities, vertical cavity tests, cryomodule validation10.430Report
MS11.1High-conductivity/temperature material characterisation11.130Report
MS11.2Vacuum and cooling proof-of-concept test completed11.136Report
MS11.3RFQ design completed11.220Report
MS11.4IH-DTL design completed11.320Report
MS11.5Collector manufactured11.434Report
MS12.1Production and characterization of 4 Cr-Gr functional prototype beam absorber blocks12.120Prototype
MS12.2Identification of alloy systems and manufacturing of first RHEA prototypes using AM and FAST/SPS12.226Report