EPITA visits ESS as accelerator facility builds up to full performance
ESS is set to host EPITA’s first annual meeting in Lund, Sweden, next year

Representatives of the EPITA project have visited the European Spallation Source in Lund, Sweden, to further build on the close ties between the project and Europe’s newest accelerator facility.
ESS is in development to become the world’s most powerful accelerator-based neutron source. When fully operational, it will deliver a pulsed proton beam with 2 MW average power to a rotating tungsten target, which, when struck, will release neutrons in a process called spallation. With an upgrade to 3MW average power in progress, and a design target of 5MW, the ESS linear accelerator (linac) is a compelling laboratory for accelerator innovation.
The facility began construction in 2014 and is closing in on producing its first neutrons in early 2027. It is a joint project involving 13 European nations and over 100 different groups in 40 institutions; as such, collaboration sits at the heart of its development.
ESS is an important partner for EPITA, and the project will hold its first annual meeting in Lund in 2027, hosted by ESS, from 19 to 21 April. Initial details are available on Indico here.
“The kind of cross-border collaboration that ESS shares with EPITA is crucial,” said Cecilia Maiano, an accelerator physicist at ESS and a task leader in the EPITA project.
“Maximising the synergy between development and operations is crucial for sharing best practices and selecting the ideal equipment for each task. By bringing together colleagues from different laboratories, we build a powerful collective expertise, while naturally enjoying the collaboration along the way,” she added.
ESS’ involvement in EPITA
ESS is participating in EPITA principally through work package 10, which aims to produce and qualify high-quality and high-gradient superconducting radio frequency (SRF) cavity prototypes at multiple frequencies. ESS is working closely with Italy’s nuclear physics institute INFN, and French research organisation CEA on tasks 10.3 and 10.4.
The goal of task 10.3 is to develop a conceptual design of an in-situ procedure to mitigate field emission activity in superconducting cavities, avoiding, if possible, the disassembling of the cavities from the hosting cryomodule.
Field emission in SRF cavities produces stray electrons (dark current) and gamma rays that add heat load, trigger false interlock trips, and can cause quenches.
The resulting radiation can also damage and activate materials, including the niobium cavities themselves, which complicates maintenance. During ESS tests, strong field emission has caused harmless but disruptive interlock trips, mainly in the coupler arc protection, that interrupt operation and can partially mask important cavity protection signals.
Task 10.3 will assess an approach to resolving this called plasma processing, in which an RF-driven plasma is ignited inside the cavity to clean the surfaces responsible for field emission. So far, nitrogen plasma has been ignited and moved selectively through all six cells of an ESS medium beta cavity in laboratory conditions.
The design will be validated in EPITA with proof-of-principle activities on prototype equipment shared within the collaboration.
Task 10.4 is diagnostics based, and aims to understand field emission, to detect it and to localise it. ESS is offering its cryomodule test stand to trial new detectors and to find ways to tell genuine arc events apart from field-emission background.
“This work being carried out in EPITA is vital for ESS because plasma processing techniques and diagnostics development address operational challenges that may arise during the long-term operation of the ESS facility,” Maiano said.
Visiting ESS’ cutting-edge site
The EPITA team were given a peek behind the curtain of ESS’ cutting-edge infrastructure, with the visit focusing on four main areas where EPITA activities are under development, but also where daily activities and tests happen: the Linac Group laboratory, the vacuum lab, the main control room and the elliptical cryomodule test stand, TS2.
Linac Laboratory:

In the linac group laboratory, small daily maintenance and development activities take place. Amongst these activities, the plasma processing preparation tests happen in collaboration with INFN-LASA colleagues: from testing the optimised radio frequency components with the proper bandwidth and performance needed for plasma ignition and characterisation, to the bead pull measurement development needed to identify the optimal modes for plasma ignition and propagation.
Main Control Room:

In ESS’ main control room, all the activities needed for the linac, linac subcomponents and linac infrastructure systems are performed and centralised.
In the control room, the visiting group met with Nuno Elias, a cryomodule cryogenics expert, who briefly presented the cryogenic system architecture for the superconducting section of the linac, and described the operator interface and necessary control systems to maintain and supervise the cryomodule operation.
Vacuum laboratory:

In the vacuum laboratory, the group met with engineer Artur Gevorgyan, who showed off a wide range of equipment.
The Vacuum Group of ESS’ Accelerator Division is equipped with a broad range of dedicated facilities, such as gauge calibration, outgassing testing, and other test rigs. These facilities support both the operation of the accelerator and the development of new projects.
The control system and remote operation are essential for the machine operation and safety, and so all the controlled equipment is tested for interlock and communication functionality.
Components, systems, and equipment operating under vacuum are routinely tested and qualified in the laboratory and on-site prior to their integration and acceptance into the machine.
TS2:

In TS2, the Site Acceptance Test of all elliptical cryomodules takes place, with the support of the IFJ-Pan team. Cryomodule qualification under nominal operational conditions takes place prior to the installation in the tunnel.
During the visit, the following areas were described: cryomodule incoming reception and preparation area, TS2 bunker and Local Control Room.